| Chronology | |
Chronology of application - from Berkeley, CA staff report, May 13, 2010
Date
|
Action
|
September 2008
|
Existing dwelling destroyed by fire
|
March 23, 2009*
|
Application Submitted, Story Poles Erected (Version 1 of Project)
|
August 17, 2009
|
Application Revised (Version 2 of Project)
|
January 7, 2010
|
Administrative Use Permit approved
|
January 27, 2010
|
Appeal submitted
|
February 22, 2010
|
Application Revised, new Story poles erected (Version 3 of Project)
|
March 11, 2010
|
ZAB Consideration: Set for hearing April 8, 2010
|
April 1, 2010
|
Mediation, presentation of Version 3 of the project plans
|
April 8, 2010
|
ZAB PHN - Staff Recommends Approval
version 3.
|
April 8, 2010
|
ZAB: Continuance
|
April 16, 2010
|
Application Revised (Version 4 of the project)
|
April 22, 2010
|
ZAB Hearing - Staff Recommends Approval version 4.
|
April 29, 2010
|
ZAB PHN
|
May 7, 2010
|
Applicant: Submittal of Revised Plans (Version 5 of Project)
|
May 13, 2010
|
ZAB Hearing - Staff Recommends Approval Revision 5
|
May 13, 2010 AUP approved unanimously by ZAB at with additional revisions
version 6 of the plans.
August 17, 2010 - Appeal of ZAB decision submitted by neighbor.
Sept 7, 2010 - two year anniversary of the fire
October 26, 2010 - ZAB decision goes to City Council for hearing. (hearing postponed by City to Nov 9)
November 9, 2010 - ZAB decision goes to City Council for hearing.
November 9, 2010 - City Council concurs with ZAB decision and dismisses appeal.
September 2011 - three year anniversary of the fire, excavation for footings finally able to begin.
May 2012 - walls arrive on site.
Feb 2013 - all walls, roof, and windows in place. Interior work underway. Narrow driveway access to hillside location has made construction a slow process.
|
|
|
|